The study on the north section of the line has been recently completed. Calgary City Council will decide on the alignment soon. The alignment would run from the Elbow River by the CPR tracks continuing along the west side of CPR and CNR tracks southward until Ogden Road where it would rejoin the CPR tracks until Glenmore Trail.
The Calgary Transit 20 Year Capital Plan (revised February 2004) has now listed the Southeast LRT line in its plans. Construction is to begin in 2019 and be completed to Douglasdale in 2023. The project is not funded and will cost an estimated $549 million.
Six stations on the North end have been planned:
- Ramsay/Inglewood
- Located: 11th Avenue SE at 10th Street SE
- Blackfoot
- Located: 26th Avenue SE at 11th Street SE near Blackfoot Trail SE
- Highfield/Bonnybrook
- Located: Highfield Blvd. SE near Ogden Road SE
- Lynnwood
- Located: West of Ogden Road SE, North of Lynnwood community
- Millican/Ogden
- Located: West of Ogden Road SE at 68th Avenue SE
- Glenmore
- Located: South of Glenmore Trail
Right-of-way has been protected for the second phase of the future line from Glenmore Trail through to McKenzie Towne.
Four stations on the South end have been planned:
- Douglasdale (Douglas Glen)
- Located: 114th Avenue SE, East of 24th Street SE
- Shepard
- Located: North side of 130th Avenue SE, West of Barlow Trail SE
- New Brighton
- Located: 52nd Street SE, South of 130th Avenue SE
- McKenzie
- Located: 52nd Street SE, South of McKenzie Towne Blvd.
For more information about future LRT plan, please take a look at the link below.
http://www.calgarytransit.com/pdf/ct_lrt_network_plan.pdf